Kelly’s program is slipping on its schedule. Management is worried that the program will be late and this will cost the organization several thousand dollars in fines and penalties. They’ve asked Kelly to use a schedule duration compression technique that will help the program finish on time . The technique that Kelly can use, however, should not add costs to the program.
What duration compression technique should Kelly use in this instance?
- A . Crash the program
- B . Add lead time to the program
- C . Trim the program scope
- D . Fast track the program
Gary is program manager for his organization. His current program is over budget and is slipping on the program schedule. Management has demanded a change to the program scope.
What is the most likely type of change management would make to this program scope?
- A . A change to add additional funds to the program scope
- B . A change to reduce the program scope
- C . Anything that management demands
- D . A change to add additional time to the program schedule
You are the program manager for your organization and you are dealing with your program stakeholders. You are explaining to them, along with your program team, how certain activities in the program may cause delays in the schedule if the associated risk events come into play . The cost of impact of the risk events are minimal, but the schedule impacts could be bigger. The stakeholders are concerned about delaying the schedule beyond a given due date for the program. They would like you to determine if it is possible to add more labor, use a higher grade of material, or hire some consultants to ensure the
risks do not occur in the program. They are not much concerned about the cost of the solution as long as the solution or identified risks do not delay the program completion.
What type of risk response are your program stakeholders recommending in this situation?
- A . Avoidance
- B . Mitigation
- C . Transference
- D . Workaround
At the beginning of the second year of a five-year strategic cycle, the program management team attends a checkpoint session to review the state of the company’s strategy. During the previous year, the company needed to comply with new government regulations that impacted this strategy.
Based on this information, what should the program manager do?
- A . Update the program management, benefits management, and risk management plans, and modify priorities and interdependencies.
- B . Meet with stakeholders, and modify the program roadmap to comply with the new regulations and ensure strategic alignment.
- C . Obtain stakeholder approval to stop or postpone programs that fail to comply with the new regulations, and modify the program roadmap.
- D . Review resource capacity and capability, program priorities, and interdependencies, and create a change request to modify the program roadmap to ensure strategic alignment.
A company is releasing a new product geared toward a specific geographic area . The program manager has received the program objectives and developed the program roadmap, which consists of six program components. Approval from the program governance board has been obtained.
What is the program manager’s next step?
- A . Assign project managers and resources
- B . Classify the program’s benefits
- C . Identify the program sponsor and program stakeholders
- D . Develop the program business case
Component project managers create project management plans for all component projects in a program . The program manager notices that some project managers prefer one status report template, while others prefer another.
How should the program manager decide which template is appropriate?
- A . Review the issue with the program management office (PMO) to determine which template to use.
- B . Review the issue with the project managers and come to mutual agreement on which template to use.
- C . Meet with the program governance board to select an appropriate template.
- D . Allow the component project managers to use their preferred templates.
You are the program manager of the YHT Program. You have been working with a vendor in the program but have decided that the contract between your program and the vendor needs to be terminated.
What two things must be documented if you wish to terminate a vendor’s contract?
- A . Contract and the quality measurements for the vendor’s work
- B . The scope verification document and the termination notice
- C . Contract and scope verification process documents
- D . Work that has been completed and uncompleted work
You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years . The program is currently 30 percent complete and you have spent $789,000 . The program is supposed to be 35 percent complete but do to some delays you’re slightly behind schedule.
Based on this information, what is the schedule variance (SV) of this program?
- A . -$85,230
- B . $821,065
- C . -$284,100
- D . -$117,295
A program manager concurrently implements a software program at four client locations . The client’s objective is to maintain quality while shortening the software implementation timeline.
What key elements should be included in the benefits register to achieve this goal?
- A . Plans for tracking and communicating risks associated with the program
- B . Plans for conducting program quality assurance and control on a regular basis
- C . Plans for program schedule control to meet the shorter timeline
- D . Plans for defining metrics and key performance indicators (KPIs), and procedures to measure benefits.
Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?
- A . Fast tracking
- B . Compressing
- C . Float
- D . Crashing