A process blade is:
- A . An organizational capability useful in solving problems
- B . A cross-functional team that works on a process
- C . A goal or vision for a particular process
- D . A meeting to discuss and arrive at process choices in a context sensitive way
Which of the following is NOT an important part of improving the WoW for a team?
- A . Do the best you can
- B . Stick to a method once you discover it
- C . Start where you are
- D . Always try to get better
Which of the following is one of the 4 views of Disciplined Agile?
- A . Technology
- B . Enterprise
- C . Mindset
- D . Goals
True or False: All of the process choices presented in a goal diagram may not be viable in a given situation
- A . FALSE
- B . TRUE
A team working on a product grew from 8 to 12 team members. The Scrum master felt that they need to split into two scrum teams. After discussion, they decided to stick to one team as it was better for team cohesiveness and delivery. This is an example of:
- A . Enterprise awareness
- B . Being Awesome
- C . Being pragmatic
- D . Optimize for flow
- E . Choice is good
Which of the following is not a role for the team lead in a Disciplined Agile team?
- A . Helping the team evolve their WoW
- B . Providing timely decisions on priority and product roadmap
- C . Guiding the team through improvement actions
- D . Helping the team collaborate
One of the differences between a MVP and a MBI is that:
- A . MVP is a collection of MBI’s
- B . MBI is typically built incrementally on top of an existing product
- C . MVP represents a product that is released to the customer
- D . MBI is the initial release that is sent to the customer
What kind of metrics are favoured in Disciplined Agile projects according to the Disciplined agile manifesto and principles?
- A . Subjective measures more than objective measures
- B . Scalar measures over trend indicators
- C . Individual measures over team measures
- D . Automated measures helping to make data driven decisions
Lean governance practices involve all of the following except:
- A . Regularly create business value
- B . Empowering the team
- C . Provide appropriate RoI
- D . Directing the team with clear tasks
- E . Present accurate and timely information
Which of the following is NOT a desirable practice in design thinking?
- A . Make design choices early in the project
- B . Be conscious about the constraints in the solution space
- C . Being empathetic to the customers
- D . Look for solutions appropriate for the situation