PMI DASM Disciplined Agile Scrum Master Online Training
PMI DASM Online Training
The questions for DASM were last updated at Nov 22,2024.
- Exam Code: DASM
- Exam Name: Disciplined Agile Scrum Master
- Certification Provider: PMI
- Latest update: Nov 22,2024
Push is when work is:
- A . Expedited to meet a deadline.
- B . Delayed until later.
- C . Given to people.
- D . Outsourced to a vendor.
How should iterations for an agile project be planned?
- A . Throughout the project by using iteration reviews to continuously improve quality.
- B . Iteratively by the product owner to ensure global optimization.
- C . At the beginning of each iteration by pulling from product backlog.
- D . At the retrospective meetings to ensure nothing is missed from one iteration to the next.
What are the eight principles of Disciplined Agile?
- A . Customer Satisfaction, Market Awareness, Be Awesome, Pragmatism, Quick Decisions, Fail Fast, Choice is Good, Customer Satisfaction.
- B . Delight Customers, Be Awesome, Pragmatism, Context Counts, Choice Good, Optimize Flow, Enterprise Awareness, Organize around products/services.
- C . Customer Satisfaction, Market Awareness, Be Awesome, Pragmatism, Context Counts, Minimize Cost, Choice is Good, Use Logic.
- D . Delight Customers, Be Awesome, Use Logic, Fail Fast, Enterprise Awareness, Optimize Process, Choice is Good, Organize around products/services.
Identify three principles of the Disciplined Agile mindset. (Choose three)
- A . Delight customers.
- B . Accelerate delivery.
- C . Enterprise awareness.
- D . Be a servant leader.
- E . Be pragmatic.
Which is not a feature of a user story?
- A . Testable
- B . Estimable
- C . Negotiable
- D . Achievable
A team has completed the work in their iteration backlog earlier than expected. There still three days left of the iteration, what should the team do now?
- A . Report the differences in completion time so the next iteration can be planned more efficiently.
- B . Wait for the other groups to complete their work prior to doing anything else.
- C . Work with the product owner to pull more work from the product backlog into their iteration backlog.
- D . Work on noncritical tasks until the product owner can them more work.
What does a well-written user story describe?
- A . A fixed outcome.
- B . The expectations of the product owner.
- C . The needs of all users.
- D . The customers’ perspective.
What is the definition of Disciplined Agile (DA)?
- A . It is an approach that frequently assesses the change within an organization to ensure all associated projects, programs, and portfolios are aligned
- B . It is a methodology that explores the various approaches to conducting agile and waterfall-based practices to project management.
- C . It is an agile set of practices that promotes autonomy within a project management office.
- D . It is a process-decision tool kit that provides straightforward guidance to help people, teams, and
organizations to streamline their processes in a context-sensitive matter.
Which approach is described as an agnostic hybrid technique that draws upon many different Ideas?
- A . Disciplined Agile
- B . Lean
- C . Iterative
- D . Agile
When should an iteration backlog be created?
- A . When planning the Kanban board or other pull method.
- B . When defining the MBI (Minimum Business Increment).
- C . At the beginning of each sprint.
- D . At the beginning of each project.