Please select the answer representing a responsibility of a Product Owner.

Please select the answer representing a responsibility of a Product Owner.
A . Ordering the items in the Product Backlog to best achieve goals and missions.
B. Defining the Definition of Done.
C. Defining the Definition of Ready.

Answer: A

Explanation:

There is no Definition of Ready in Scrum.

Latest PSPO-I Dumps Valid Version with 481 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments