Pierre is constructing a tender for a security contract. As well as cost, he would like to ask the security companies some questions about their health and safety processes and staff qualifications. He has created several questions and weighted these so that they add up to 25. is this the correct thing to do?
Pierre is constructing a tender for a security contract. As well as cost, he would like to ask the security companies some questions about their health and safety processes and staff qualifications. He has created several questions and weighted these so that they add up to 25. is this the correct thing to do?
A . yes- point systems can be weighted any way a buyer choses so long as this is explained in the ITT
B . yes- 25 is the correct weighting for quality question
C . no- the weighting should total 10
D . no- the weighting should total 100
Answer: D
Explanation:
weighted points systems for assessments should add up to 100. This is 100%.
An example is how this would work is
Price = 50%
Health and Safety questions= 30%
Qualifications = 20%