page layouts?

When should both the Root Work Order and Root Work Order Line Item fields be added to

page layouts?
A . When a service process dictates that there are two levels in a Work Order Hierarchy and two levels in the Work Order Line Hierarchy. (Parent Work Order can be used)
B . When a service process dictates that there is a single level in a Work Order Hierarchy and more than two levels in the Work Order Line Hierarchy.
C . When a service process dictates that there are more than two levels in a Work Order Hierarchy and more than two levels in the Work Order Line Hierarchy.
D . When a service process dictates that there are more than two levels in a Work Order Hierarchy and more than a single level in the Work Order Line Hierarchy.

Answer: C