Exam4Training

‘Open tendering may impose a substantial administrative burden on the procurement function.’ True or false?

‘Open tendering may impose a substantial administrative burden on the procurement function.’ True or false?
A . True
B . False

Answer: A

Explanation:

Because a wide range of organisations (or even individuals) may respond to an open tender, considerable administrative resource may have to be devoted to analysing offers.

Latest L3M1 Dumps Valid Version with 90 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version