‘Open tendering may impose a substantial administrative burden on the procurement function.’ True or false?

‘Open tendering may impose a substantial administrative burden on the procurement function.’ True or false?
A . True
B . False

Answer: A

Explanation:

Because a wide range of organisations (or even individuals) may respond to an open tender, considerable administrative resource may have to be devoted to analysing offers.