On which elements of the engagement is the Residual Risk field in the engagement summary based?
A . Grades submitted on risk assessment questionnaires
B . to the inherent risk screening questionnaire
C . Issues created during the engagement request process
D . Controls triggered during the engagement request process
Answer: D