You are the Scrum Master for a project in a new Scrum environment. The Development Team is confused about their responsibilities in a Sprint.
Of the following which one is not part of the Development Team’s responsibilities?
A . The Development Team will consult on user stories for the Product Backlog.
B. The Development Team chooses the Product Owner for each Sprint.
C. The Development Team determines who’ll do what task in the Sprint Backlog.
D. The Development Team will estimate the work of Product Backlog.
Answer: B