Of the following steps in the process of developing a cohesive early-project Strategy Design, which one is responsible for: Ensuring that the team is working for a goal that is meaningful and will bring valuable benefits to the organization?
Of the following steps in the process of developing a cohesive early-project Strategy Design, which one is responsible for: Ensuring that the team is working for a goal that is meaningful and will bring valuable benefits to the organization?
A . Project Research
B. Idea Generation
C. Challenge Framing
D. Craft of Key insights
Answer: C