Nexus Integration team has defined a Definition of Done with 5 point criteria. One of the Sprint Team, want to use only 3 of them for their team’s Definition of Done. Is this allowed?
A . No
B. Yes
Answer: A
Explanation:
Individual Scrum Teams may choose to apply a more stringent definition of Done within their own teams, but cannot apply less rigorous criteria than agreed for the Increment.