NEXT in the operational infrastructure change process?

After determining the appropriate maintenance window, which of the following should occur

NEXT in the operational infrastructure change process?
A . Implement the change.
B. Approve the test plan.
C. Notify customers.
D. Develop a rollback plan.

Answer: D

Explanation:

The project manager should develop a rollback plan next after determining the appropriate maintenance window in the operational infrastructure change process. A rollback plan is a contingency plan that describes how to revert to the previous state of the system or infrastructure in case of a failure or disruption during the change implementation. A rollback plan can help to minimize the impact and risk of the change and ensure business continuity and stability.