In the event of a conflict between the Product Data Sheet and the Specification:
In the event of a conflict between the Product Data Sheet and the Specification:A . The Product Data Sheet prevailsB . The Specification prevailsC . It is up to the Inspector to decide which one to followD . It is up to the Applicator to decide which one to followView...
The standards defining surface cleanliness achieved by centrifugal blast cleaning are:
The standards defining surface cleanliness achieved by centrifugal blast cleaning are:A . Different than air blast cleaningB . The same as air blast cleaningC . Slightly different to air blast cleaningD . Comparable to air blast cleaningView AnswerAnswer: B
NACE No.13/ SSPC 6 identifies the use of:
NACE No.13/ SSPC 6 identifies the use of:A . Abrasive blasting onlyB . Watterjetting onlyC . Steam cleaning onlyD . Various methods of cleaningView AnswerAnswer: D
The coating applicator has ignored a enface preparation hold point and applied coating over the surface without a sign off from you as the inspector.
The coating applicator has ignored a enface preparation hold point and applied coating over the surface without a sign off from you as the inspector. Your FIRST preferred course of action is to:A . Stop the jobB . Require the Applicator to remove the coatingC . Advise the Owner and...
Individuals conducting Coating Surveys should:
Individuals conducting Coating Surveys should:A . Always be NACE Level 3 Certified InspectorsB . Always be NACE or SSPC Protective coating SpecialistsC . Always be experienced Specification WritersD . Always be trained and experienced Coating IndustryView AnswerAnswer: D
You are working as the only in-house NACE Level 2 Inspector in a shop setting when an independent 3 rd party NACE Level 3 Inspector, representing the owner, presents you with a copy of a Non Conformance Report (NCR) he has written for a NACE2/SSPC SP 10 centrifugal blast which you had previously approved.
You are working as the only in-house NACE Level 2 Inspector in a shop setting when an independent 3 rd party NACE Level 3 Inspector, representing the owner, presents you with a copy of a Non Conformance Report (NCR) he has written for a NACE2/SSPC SP 10 centrifugal blast which...
You are NACE Level 2 Inspector working on a tank lining job where a mobile centrifugal blast unit is being used to blast the tank floor to a NACE No.1/SSPC SP 5. The Contractor has completed his final blast and has called for a hold point inspection. This is the 1 st time you have seen field based centrifugal blast cleaning. You observe what appears to be staining on the substrate however the Contractor assures you this is normal when using centrifugal blast units and what you are seeing is what is defined in the standard as an acceptable variation in appearance.
You are NACE Level 2 Inspector working on a tank lining job where a mobile centrifugal blast unit is being used to blast the tank floor to a NACE No.1/SSPC SP 5. The Contractor has completed his final blast and has called for a hold point inspection. This is the...
An Inspection and Test Plan is required when:
An Inspection and Test Plan is required when:A . It is always requiredB . When the Coating Applicator requests oneC . When the Owner specifies oneD . When the Inspector requests oneView AnswerAnswer: C
The cost of qualified Coating Inspection is normally offset by:
The cost of qualified Coating Inspection is normally offset by:A . Lower Application CostsB . Lower Coating Life Cycle CostsC . Lower Safety Enforcement CostsD . Lower Supervision CostsView AnswerAnswer: B
Eddy current DFT gauges are used to measure Dry Film Thickness in which of the following situations:
Eddy current DFT gauges are used to measure Dry Film Thickness in which of the following situations:A . Magnetic coatings applied to a magnetic metallic substrateB . Non-Conductive coatings applied to a conductive metallic substrateC . Conductive coatings applied to a magnetic metallic substrateD . Conductive coatings applied to a...