A single component water borne acrylic coating cures by:
A single component water borne acrylic coating cures by:A . Solvent EvaporationB . CoalescenceC . Co-ReactionD . OxidationView AnswerAnswer: B
When environmental enclosures are being used an inspector needs to be concerned about:
When environmental enclosures are being used an inspector needs to be concerned about:A . LightingB . Air changesC . Structural integrityD . a), b), and c)View AnswerAnswer: D
It is always possible to see moisture on a steel substrate:
It is always possible to see moisture on a steel substrate:A . TrueB . FalseView AnswerAnswer: B
When observing fabrication defects the NACE Inspector should:
When observing fabrication defects the NACE Inspector should:A . Require they be corrected prior to coatingB . Consult the specification to determine how they should be treatedC . Stop the job immediatelyD . Write an NCR and call the fabricatorView AnswerAnswer: B
WJ-1 is always performed using UHWJ at pressures above 210 MPa (30,000 PSI)
WJ-1 is always performed using UHWJ at pressures above 210 MPa (30,000 PSI)A . TrueB . FalseView AnswerAnswer: A
Surface preparation methods for Non-ferrous metals are:
Surface preparation methods for Non-ferrous metals are:A . The same as for Ferrous metalsB . The same for all Non-FetT0us metalsC . Specific for each type of Non-ferrous metalD . Not requiredView AnswerAnswer: C
You are working as an inspector in a galvanizing plant for the first time.
You are working as an inspector in a galvanizing plant for the first time. What are some of the hazards you need to be aware of:A . Risk of chemical exposureB . Risk of skinC . Risk of acid or caustic splashesD . a), b), and c)View AnswerAnswer: D
You are the NACE Coating Inspector on a tank lining project and are asked to perform a high voltage holiday test after the coating applicators have completed their final repairs. After meeting all the confined space entry permit you enter the tank and notice a very strong odor of solvent.
You are the NACE Coating Inspector on a tank lining project and are asked to perform a high voltage holiday test after the coating applicators have completed their final repairs. After meeting all the confined space entry permit you enter the tank and notice a very strong odor of solvent....
You are the NACE Inspector on a project where a stationary floating structure is being coated and you notice a self-smoothing anti-fouling coating has been specified.
You are the NACE Inspector on a project where a stationary floating structure is being coated and you notice a self-smoothing anti-fouling coating has been specified. This is not a good choice because:A . It contains biocideB . It doesn't contain biocideC . The floating structure is stationaryD . It...
You are a NACE Level 2 Coating Inspector who has just arrived on a job in progress where there is no Inspection and Test Plan (ITP). The first morning you arrive the job is behind schedule and you are asked to take DIY Film Thickness readings.
You are a NACE Level 2 Coating Inspector who has just arrived on a job in progress where there is no Inspection and Test Plan (ITP). The first morning you arrive the job is behind schedule and you are asked to take DIY Film Thickness readings. Your FIRST preferred course...