When observing fabrication defects the NACE Inspector should:
When observing fabrication defects the NACE Inspector should:A . Require they be corrected prior to coatingB . Consult the specification to determine how they should be treatedC . Stop the job immediatelyD . Write an NCR and call the fabricatorView AnswerAnswer: B
You are the NACY Coating Inspector on a tank lining project where desiccant dehumidification is being used. Since the first shift of abrasive blasting your readings have indicated relative humidity below 40%; however on the second shift of coating application your readings are indicting 80%.
You are the NACY Coating Inspector on a tank lining project where desiccant dehumidification is being used. Since the first shift of abrasive blasting your readings have indicated relative humidity below 40%; however on the second shift of coating application your readings are indicting 80%. Your FIRST preferred course of...
NACE No.13/ SSPC 6 identifies the use of:
NACE No.13/ SSPC 6 identifies the use of:A . Abrasive blasting onlyB . Watterjetting onlyC . Steam cleaning onlyD . Various methods of cleaningView AnswerAnswer: D
Coating Surveys are legally required:
Coating Surveys are legally required:A . On commercial marine vessels and offshore platformsB . On high pressure gas lines and fireproofed structuresC . On water tanks and potable water pipelinesD . On food and beverage vessels and can liningsView AnswerAnswer: A
From a corrosion perspective, the main difference between Ferrous and Non-Ferrous Metals is:
From a corrosion perspective, the main difference between Ferrous and Non-Ferrous Metals is:A . CostB . Iron contentC . AppearanceD . SafetyView AnswerAnswer: B
The Concrete Repair Institute's comparators can be used to assess:
The Concrete Repair Institute's comparators can be used to assess:A . Surface cleanliness prior to coatingB . Surface profile prior to coatingC . Contamination levels prior to coatingD . Compressive and tensile strength prior to coatingView AnswerAnswer: B
You are NACE Level 2 Inspector working on a tank lining job where a mobile centrifugal blast unit is being used to blast the tank floor to a NACE No.1/SSPC SP 5. The Contractor has completed his final blast and has called for a hold point inspection. This is the 1 st time you have seen field based centrifugal blast cleaning. You observe what appears to be staining on the substrate however the Contractor assures you this is normal when using centrifugal blast units and what you are seeing is what is defined in the standard as an acceptable variation in appearance.
You are NACE Level 2 Inspector working on a tank lining job where a mobile centrifugal blast unit is being used to blast the tank floor to a NACE No.1/SSPC SP 5. The Contractor has completed his final blast and has called for a hold point inspection. This is the...
When observing design defects the NACE Inspector should:
When observing design defects the NACE Inspector should:A . Document the defect and the potential problems that could resultB . Ignore the defect as the inspector can’t change the designC . Request that the item be rebuilt with a better design for coatingD . Stop the job immediatelyView AnswerAnswer: A
You are the NACE Level 2 Coating Inspector where SSPC PA 2 has been specified with an additional requirement that no individual gauge reading shall be below a certain value.
You are the NACE Level 2 Coating Inspector where SSPC PA 2 has been specified with an additional requirement that no individual gauge reading shall be below a certain value. As this is not part of the standard you should:A . Ignore the additional requirementB . Enforce the additional requirementC...
In the event of a conflict between the Product Data Sheet and the Specification:
In the event of a conflict between the Product Data Sheet and the Specification:A . The Product Data Sheet prevailsB . The Specification prevailsC . It is up to the Inspector to decide which one to followD . It is up to the Applicator to decide which one to followView...