When applying the vision governance theme, which is an area of focus for the senior responsible owner?
When applying the vision governance theme, which is an area of focus for the senior responsible owner?A . To ensure that the vision statement supports the programme communications planB . To ensure that the organization is capable of achieving the transformation describedC . To deliver the operational changes needed to...
Which information about a project should be included in the Projects Dossier?
Which information about a project should be included in the Projects Dossier?A . How the outputs will be implemented into the businessB . Contribution the project will make to the programme’s benefitsC . Names of the project team membersD . Project brief for the projectView AnswerAnswer: A Explanation: Reference: https://community.simplilearn.com/threads/what-is-project-dossier.211/
Which is the BEST description of the purpose of the Projects Dossier?
Which is the BEST description of the purpose of the Projects Dossier?A . Lists the projects involved in the delivery of the BlueprintB . Specifies a thorough brief for starting each projectC . Describes the context when starting up projectsD . Provides detailed requirements for each projectView AnswerAnswer: A Explanation:...
Which is a transformational flow process?
Which is a transformational flow process?A . Monitoring and Control StrategyB . Issue Management CycleC . Planning and ControlD . Managing the TranchesView AnswerAnswer: D Explanation: Reference: https://www.simplilearn.com/transformational-flow-overview-tutorial
Why should stakeholders’ influence and interests be compared?
Why should stakeholders’ influence and interests be compared?A . To define the areas of the programme that affect each stakeholderB . To identify the various stakeholders from their interestsC . To ensure communication channels are exploited effectivelyD . To understand how the programme will affect their working environmentView AnswerAnswer: D
Which risk response encourages collaboration on risk management activities?
Which risk response encourages collaboration on risk management activities?A . AvoidB . ReduceC . ShareD . Prepare contingent plansView AnswerAnswer: C Explanation: Reference: https://www.simplilearn.com/overview-of-risk-and-issue-management-tutorial
Which governance theme includes carrying out an assessment of the effectiveness of the decisions taken by programme leaders?
Which governance theme includes carrying out an assessment of the effectiveness of the decisions taken by programme leaders?A . Blueprint Design and DeliveryB . Leadership and Stakeholder EngagementC . Quality and Assurance ManagementD . Programme OrganizationView AnswerAnswer: B
Which is NOT normally a characteristic of a Vision Statement?
Which is NOT normally a characteristic of a Vision Statement?A . Defines benefits indirectlyB . Helps understand the need for changeC . Describes intermediate future statesD . Provides basis for development of the BlueprintView AnswerAnswer: A
Which is a trigger for a compliance programme?
Which is a trigger for a compliance programme?A . The corporate board has created a vision for changeB . A number of stand-alone projects would benefit from better coordinationC . The organization has to change to meet requirements of new legislationD . The organization chooses to take a new innovative...
Include the costs of a contingency budget for dealing with risk.
Include the costs of a contingency budget for dealing with risk.A . Only 1 is trueB . Only 2 is trueC . Both 1 and 2 are trueD . Neither 1 and 2 are trueView AnswerAnswer: A Explanation: Reference: https://www.simplilearn.com/introduction-to-business-case-tutorial