MRP software is applied to schedule which of the following?

MRP software is applied to schedule which of the following?
A . Tax accounting
B. Production processes
C. Human resource management
D. Executive meetings

Answer: B

Explanation:

Material Requirements Planning (MRP) software manages material requirements for manufacturing processes.

LO 2, AC 2.3