In which order should you perform the actions?
DRAG DROP A company implements Dynamic 365 for Finance and Operations. You run the latest master plan. You observe invalid results. You need to set up tracing for the master plan. In which order should you perform the actions? To answer, move all actions from the list of actions to...
Which three actions should you perform?
A company implements Dynamics 365 Supply Chain Management. Due to increased demand and limited space in the work cell area for product L0050, you must subcontract overflow work to another company. You have the following requirements: ✑ Locate a warehouse at the subcontractor building. ✑ Support picking and shipping activity...
How should you set up the item?
A company uses Process manufacturing for most products and Discreet manufacturing for other products. The company is creating a formula for a new product. The new item will be used to make a name brand product and two generic brand products. This item has the following requirements: • Production of...
Which four actions should you perform in sequence?
DRAG DROP A company overstates on-hand raw materials due to the time it takes to post raw materials when production orders are processed. All items used to manufacture finished goods must be consumed when a finished good is reported as finished. You must not change all bill of materials lines...
Which two options can you use?
A company produces paints and assembles bicycle frames. You must account for paint drying time before assembly operations can begin. You need to set up the operation to encompass queue times. Which two options can you use? Each correct answer presents part of solution. NOTE: Each correct selection is worth...
Which type of manufacturing should you implement?
A company is looking to use Dynamics 365 Supply Chain Management. The company is in the process of redesigning and retooling an existing manufacturing plant to support a large long-running contract. They want to be able to forecast capacity to easily ramp up for additional products. You need to set...
What three setup configurations must you validate?
A manufacturing company uses advanced warehouse management functionality for a new warehouse. After releasing a production order, you observe that the warehouse work for raw material picking was not generated. You need to go through the warehouse management setup to determine what is missing. What three setup configurations must you...
A company implements Dynamics 365 Supply Chain Management
HOTSPOT A company implements Dynamics 365 Supply Chain Management. Production orders are generated for products directly from projects. You create the following production order: Use the drop-down menus to select the answer choice that answers each question based on the information presented in the graphic. NOTE: Each correct selection is...
In which order should you perform the actions?
DRAG DROP A configure-to-order company is implementing Dynamics 365 Supply Chain Management. The company is preparing to use the product configuration model functionality to develop the Bill of materials (BOM), routes and valid configuration combinations. You need to set up the configuration models, constraints, and pricing. In which order should...
What three actions should you perform?
You are the production supervisor at a chemical processing plant. You must track attributes for each batch of chemicals. Automated quality orders must be generated when a batch order for these chemicals is reported as finished. You need to ensure that the values of attributes are updated and tracked. What...