You need to know which future tasks could be affected as a result of the resource leaving your project.What should you do?
You use Project Professional 2013 to manage a project schedule which includes all task relationships.The resource who is assigned to the “Develop software delivery” task is no longer available to work on your project.You can find another resource to perform this task, but you are not sure when the resource will become...
You are a project manager for a company that uses Project Professional 2013.You are developing a schedule and plan to use the leveling order of Priority, Standard.You need to create a task which leveling will not change.What should you do?
You are a project manager for a company that uses Project Professional 2013.You are developing a schedule and plan to use the leveling order of Priority, Standard.You need to create a task which leveling will not change.What should you do?A . Set task priority to 1000.B . Set task priority to 0.C . Set task priority to...
Your company uses Project Professional 2013.You are scheduling two tasks.One task is named Test Solution, and the other task is named Create Solution Test Plan.You want the Test Solution task to start three working days after the finish date of the Create Solution Test Plan task.You need to set up a dependency between these two tasks.What should you do?
Your company uses Project Professional 2013.You are scheduling two tasks.One task is named Test Solution, and the other task is named Create Solution Test Plan.You want the Test Solution task to start three working days after the finish date of the Create Solution Test Plan task.You need to set up a dependency between these two...
You are a project manager who uses Project Professional 2013.You need to change the default for all new projects so that tasks will be created in Auto Scheduled mode.What should you do?
You are a project manager who uses Project Professional 2013.You need to change the default for all new projects so that tasks will be created in Auto Scheduled mode.What should you do?A . For each new project, use the Status Bar to set new tasks to be auto scheduled.B . Set the Default task type to Auto Scheduled...
What should you do?
Your organization uses Project Professional 2013 and Microsoft SharePoint 2013.You are responsible for a project with resources in different offices.All offices share the same SharePoint intranet, and all resources have valid accounts to log into the company intranet.Your project plan already has the correct names and assignments for each resource involved in this...
You are a project manager who uses Project Standard 2013.You are creating a preliminary project schedule and are estimating the number of resources required prior to finalizing the schedule.You do not have named resources to complete the tasks, but you know the resource roles that are necessary.One of the roles needed is architect.You need to estimate how many architect hours are required to complete the work.What should you do?
You are a project manager who uses Project Standard 2013.You are creating a preliminary project schedule and are estimating the number of resources required prior to finalizing the schedule.You do not have named resources to complete the tasks, but you know the resource roles that are necessary.One of the roles needed is...
You are a project manager who uses Project Professional 2013.You have worked on a project for four years and have created a very detailed project plan in Project Professional 2013.You use milestones as key deliverables, and you use summary tasks as phases.Your company requests a presentation of the key deliverables for each phase of your project plan in a simple and consolidated view that fits in one Microsoft PowerPoint slide.You need to ensure that phases and key deliverables are clearly shown in the timeline and are not confusing to the audience.What should you do?
You are a project manager who uses Project Professional 2013.You have worked on a project for four years and have created a very detailed project plan in Project Professional 2013.You use milestones as key deliverables, and you use summary tasks as phases.Your company requests a presentation of the key deliverables for each...