You are a project manager for a software development company that uses Project Professional 2013.For managing projects, your company has its own specialized processes, all of which you are familiar with, except for the reporting processes.Additionally, your company’s status reports of project progress are based on Work and Cumulative Work.Thirty minutes before a meeting is scheduled to begin, the president of your company asks you to present the status report at the meeting.You need the report to show all project tasks, resources assigned, and their respective Work and Cumulative Work on a monthly basis.What should you do?
You are a project manager for a software development company that uses Project Professional 2013.For managing projects, your company has its own specialized processes, all of which you are familiar with, except for the reporting processes.Additionally, your company’s status reports of project progress are based on Work and Cumulative Work.Thirty minutes before...
What should you do?
You are a project manager who uses Project Professional 2013.You are creating a project with several phases.Your customer requires the delivery phase of the project to start on July 1 and to finish within four weeks.The delivery phase includes a summary task, which consists of five separate sub tasks.You need to monitor this...
What should you do?
You are a project manager who uses Project Professional 2013.You work on a construction project that requires propane as a fuel source for your equipment.The foreman requires that you enter project costs associated with all work completed on your project.The propane costs $5.00 per gallon, and the tank holds 500 gallons of propane.Each time the tank is refilled, you must...
What should you do?
You manage a project for an organization that relies heavily on schedule baselines in Project Standard 2013.A change is approved for an in-progress project which you manage.You enter the new tasks necessary to include the changes to the project schedule.You need to update the baseline in the most efficient manner. What should you do?A...
You need to resolve the negative Total Slack values.What should you do?
You are a project manager who uses Project Professional 2013.When viewing the critical path, you notice that there are some inconsistencies.To investigate the status of the critical path, you insert the Total Slack column into a task table.You discover that many of the tasks have negative Total Slack values. You need to resolve...
You need a graphical view that shows the current schedule to baseline.Which view should you use?
You are a project manager who uses Project Professional 2013.After updating a project schedule, you want to determine the amount of time that the schedule has slipped from the original scheduled dates. You need a graphical view that shows the current schedule to baseline.Which view should you use?A . Tracking Gantt viewB . Leveling...
You are a project manager who uses Project Standard 2013.You regularly customize the Bar Styles for a project prior to printing the project schedule.You need to add the Bar Styles button to the Quick Access Toolbar as quickly as possible.What are two ways to achieve this goal? (Each correct answer presents a complete solution.Choose two.)
You are a project manager who uses Project Standard 2013.You regularly customize the Bar Styles for a project prior to printing the project schedule.You need to add the Bar Styles button to the Quick Access Toolbar as quickly as possible.What are two ways to achieve this goal? (Each correct answer presents a complete solution.Choose two.)A ....
What should you do?
You are managing a project using Project Professional 2013. Your project schedule is showing task overallocation indicators in the Gantt chart view.You navigate to the Team Planner view to investigate more details regarding the over allocations. You discover that the BA1 resource is overallocated and you need to see all assignments with details...
You are a project manager, and your organization uses Project Professional 2013.You have created a detailed project schedule and have identified two tasks that are causing your resource to be overallocated.You need to use the Team Planner to reassign these tasks from the overallocated resources to underallocated resources with the same skill set.What should you do?
You are a project manager, and your organization uses Project Professional 2013.You have created a detailed project schedule and have identified two tasks that are causing your resource to be overallocated.You need to use the Team Planner to reassign these tasks from the overallocated resources to underallocated resources with the same skill set.What should...
You are a project manager who uses Project Standard 2013.Your current project has resources with the standard calendar as the base calendar.Some tasks of the project need to be done overnight so the night shift calendar is assigned to those tasks.When you assign a resource to one of these tasks, you get an error.You need to correctly assign the resource.What should you do?
You are a project manager who uses Project Standard 2013.Your current project has resources with the standard calendar as the base calendar.Some tasks of the project need to be done overnight so the night shift calendar is assigned to those tasks.When you assign a resource to one of these tasks, you get...