Microsoft MB-335 Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert Online Training
Microsoft MB-335 Online Training
The questions for MB-335 were last updated at Feb 21,2025.
- Exam Code: MB-335
- Exam Name: Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert
- Certification Provider: Microsoft
- Latest update: Feb 21,2025
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to It. As a result, these questions will not appear in the review screen.
A manufacturing plant uses Lean processes. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service. You need to create a subcontracting activity for the painting service.
Solution:
• Create a purchase agreement for the subcontracting vendor and add SP-01 as the painting service.
• Create a vendor resource then create a work cell for outsourced painting and add the resource to the work cell.
• Create a production flow process activity for the painting work cell and add the component to be painted as a picking activity.
• Create a server term to tie the purchase agreement to the activity.
Does the solution meet the goal?
- A . Yes
- B . No
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A manufacturing plant uses Lean processes. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service. You need to create a subcontracting activity for the painting service.
Solution:
• Create a purchase agreement for the subcontracting vendor that contains the pricing information for SP-01.
• Create a vendor resource and a work cell for outsourced painting, then add the resource to the work cell.
• Create a production flow process activity using the painting work cell and the service item as the picking activity.
• Create a service term on the activity to tie the purchase agreement to the activity.
Does the solution meet the goal?
- A . Yes
- B . No
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A manufacturing company has a new speaker that is available with standard and premium carbon fiber options.
For the premium option, speakers are made to order. Customers can choose from seven product attributes at different prices.
You need to create and configure the product and pricing for the new speaker.
Solution: Create a constraint-based product with configurations. Use a price model to calculate the different configurable option costs.
Does the solution meet the goal?
- A . Yes
- B . No
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company implements Dynamics 365 Supply Chain Management and configures the system to support process manufacturing.
The company manufactures pain-relieving lotions. Several of the primary ingredients are delivered at different concentrations depending on the ingredient and vendor. Ingredient A is the primary active ingredient in the lotion. Ingredient B is used as a compensating ingredient. You need to ensure that the system is set up to support the manufacturing process.
Solution: Create a dimension-based product master with variants and use the trade agreements to specify the different pricing.
Does the solution meet the goal?
- A . Yes
- B . No
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company implements Dynamics 365 Supply Chain Management and configures the system to support process manufacturing.
The company manufactures pain-relieving lotions. Several of the primary ingredients are delivered at different concentrations depending on the ingredient and vendor. Ingredient A is the primary active ingredient in the lotion. Ingredient B is used as a compensating ingredient. You need to ensure that the system is set up to support the manufacturing process.
Solution: Create a dimension-based product with configurations. Use a price model to calculate the different configurable option costs.
Does the solution meet the goal?
- A . Yes
- B . No
DRAG DROP –
You are the quality assurance manager of a pharmaceuticals company.
One of your customers has requested to only receive batches of item B0001 that have an acid concentration between 5.5 C 10.5 percent.
You need to set up the customer specific batch attribute to track percent acid for B0001.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
A manufacturer uses Dynamics 365 Supply Chain Management to build bicycles.
When manufacturing releases production orders to the warehouse, the warehouse must avoid automatically releasing the bill of materials (BOM) and formula lines. The BOM and formula lines must be manually released later through a batch process. You need to configure the functionality for the records.
At which two locations should you configure this functionality? Each correct answer presents a complete solution. NOTE: Each correct selection is worth one point.
- A . site
- B . warehouse
- C . production order
- D . legal entity
- E . item model group
HOTSPOT –
A company implements Dynamics 365 Supply Chain Management. The company is setting up a production line to make a new product.
The new production line will run three shifts five days a week. Each shift produces 100 widgets. Each machine performs specific functions that represent a sequenced step in the manufacturing process. The process requires the use of a qualified machinist. One of the machinists who
oats among machines requires time off for appointments every Tuesday and Thursday afternoon.
You must be able to track the availability of the floating worker and each machine, as well as schedule production orders for the new line based on capacity to perform the work.
You need to configure the route.
Which configuration option should you use? To answer, select the appropriate options in the answer area. NOTE: Each correct selection is worth one point.
DRAG DROP
A manufacturer uses route operations and job scheduling. You use a unique calendar for a conveyor line.
The company observes a decrease in the number of hours a conveyor line resource is operational due to breakdowns. You must make a temporary change to the number of hours the resource is available.
You need to adjust the efficiency percentage for the conveyor line calendar.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item.
This item has the following Lean setup:
The setup uses a Lean schedule group with a throughput ratio = 2.
The process activity tied to production ow has the following runtime activity times: time = 3 min, per quantity = 1.
The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8 hour day).
The throughput is 10 per hour.
You need to set up a Discrete operation to mirror the item’s production ow activity.
What should you do?
- A . Create a route with a runtime = 6, a process quantity = 1, and the operation’s hours/time = 1.
- B . Create a route with a runtime = 6, a process quantity = 1, and the operation’s hours/time = 0.0167 (e.g. 1 hour/60 minutes).
- C . Create a route with a runtime = 1, a process quantity = 6, and the operation’s hours/time = 0.0167 (e.g. 1 hour/60 minutes).
- D . Create a route with a runtime = 1, a process quantity = 1, and the operation’s hours/time = 0.0167 (e.g. 1 hour/60 minutes).