Listed below are some risks and issues that might be encountered during the course of a project. Identify which of the following are risks (not issues).

Listed below are some risks and issues that might be encountered during the course of a project. Identify which of the following are risks (not issues).

A) After extensive training, marketing representatives might still not be ready to take orders after the project is launched.

B) The painting crew might be delayed due to heavy rain, which could negatively impact the project schedule.

C) Funding was not approved.

D) Requirements, as currently defined, are unclear.
A . Only
B. A and C
C. and D
D. A and B

Answer: B

Latest ASM Dumps Valid Version with 39 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments