It is the phase for implementation roadmap where you document the business process requirements of the company. Activities include alignment of customers’ business and technical requirements to the SAP standard software.

It is the phase for implementation roadmap where you document the business process requirements of the company. Activities include alignment of customers’ business and technical requirements to the SAP standard software.
A . Project Preparation
B . Business Blueprint
C . Realization
D . Final Preparation
E . Go Live and Support

Answer: B