Choose the VALID description of the ramp-up concept.
- A . Stage of reaching the stationary state.
- B . Stage of finishing the test.
- C . Stage of exit from a stationary state by increasing the number of concurrent users.
- D . Technique in which the load on the system is increased to a certain value in the shortest possible time.
Choose the VALID description of the ramp-up concept.
- A . Stage of reaching the stationary state.
- B . Stage of finishing the test.
- C . Stage of exit from a stationary state by increasing the number of concurrent users.
- D . Technique in which the load on the system is increased to a certain value in the shortest possible time.
Choose the VALID description of the ramp-up concept.
- A . Stage of reaching the stationary state.
- B . Stage of finishing the test.
- C . Stage of exit from a stationary state by increasing the number of concurrent users.
- D . Technique in which the load on the system is increased to a certain value in the shortest possible time.
Choose the VALID description of the ramp-up concept.
- A . Stage of reaching the stationary state.
- B . Stage of finishing the test.
- C . Stage of exit from a stationary state by increasing the number of concurrent users.
- D . Technique in which the load on the system is increased to a certain value in the shortest possible time.
Choose the VALID description of the ramp-up concept.
- A . Stage of reaching the stationary state.
- B . Stage of finishing the test.
- C . Stage of exit from a stationary state by increasing the number of concurrent users.
- D . Technique in which the load on the system is increased to a certain value in the shortest possible time.
The default error handling of the performance test tools Is sufficient, so no additional checks need to be introduced.
- A . True statements: II, IV.
- B . True statements: 111, V.
- C . True statements: III, IV.
- D . True statements: I, IV.
If a performance test is testing the response time of an application to be connected through remote
access, which protocol is being used?
- A . MMS.
- B . RTE.
- C . WSCL.
- D . LDAP.
If a performance test is testing the response time of an application to be connected through remote
access, which protocol is being used?
- A . MMS.
- B . RTE.
- C . WSCL.
- D . LDAP.
If a performance test is testing the response time of an application to be connected through remote
access, which protocol is being used?
- A . MMS.
- B . RTE.
- C . WSCL.
- D . LDAP.
If a performance test is testing the response time of an application to be connected through remote
access, which protocol is being used?
- A . MMS.
- B . RTE.
- C . WSCL.
- D . LDAP.