Use the ‘Additional Information’ in the Scenario Booklet to answer this question.
The Operations Director is the executive for the project and has proposed that a senior course developer be appointed as project manager. The course developer works in the Training Development Manager’s team and has a good understanding of the standard course development model. The course developer was a team manager on a previous project for which the Operations Director was the executive.
Is this proposed appointment appropriate, and why?
A . Yes, because the course developer is responsible for ensuring that trainers deliver courses to the required standard.
B . Yes, because the course developer is likely to have the project management and specialist knowledge required.
C . No, because the course developer’s team reports to the Business Development Director, not the Operations Director.
D . No, because there is a conflict of interest as the Training Development Manager is responsible for gaining accreditation.
Answer: B