Is this appropriate, and why?
ABC Company uses a standard development model to develop courses and uses PRINCE2 to manage
these projects. The objectives from the Health and Safety Training Project have been documented in the
business plan of ABC Company. This business plan has triggered this project. As a result, to save time,
the executive has decided to simplify the ‘starting up a project’ process. The project mandate will be
adapted and becomes the project brief.
Is this appropriate, and why?
A . Yes, because the business outcomes are clear, the project brief can be a sample statement elaborating the mandate.
B . Yes, because the executive can initiate the project based on the project mandate by passing the ‘starting up a project’ process.
C . No, because the project brief should be a statement which includes a fuller description of the project.
D . No, because capturing lessons from previous projects identify lessons to be applied to this project.
Answer: C