Is this an appropriate application of the ‘tailor to suit the project’ principle, and why?
ABC Company has a standard course development model with four defined stages that the company manages using PRINCE2. The project manager for the Health and Safety Training Project has recommended the stage 2 of the standard model be split into two separate stages. As a result, there will now be five management stages in the project.
Is this an appropriate application of the ‘tailor to suit the project’ principle, and why?
A . Yes, because the project manager can adapt or combine PRINCE2 process to suit the project.
B . Yes, because the standard course development structure should be tailored to suit the project.
C . No, because a simple project should have no more than two management stages.
D . No, because the standard course development structure should be applied to the project.
Answer: B
Latest PRINCE2Practitioner Dumps Valid Version with 282 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund