ABC Company has decided to include the Health and Safety Training Project in a programme to support their strategy to deliver globally. The programme team has provided the detailed business justification and, as a result, the project board has decided that the business case will not need refining further during the ‘initiating a project’ process.
Is this an appropriate action for the project board, and why?
A . Yes, because the project board are able to use the business case provided by the programme.
B . Yes, because when the project is part of a programme, the programme team provides the business case.
C . No, because the programme team cannot constrain the project manager’s choices.
D . No, because each project in the programme will need a revised business case.
Answer: A