Is it a good idea it the Product Owner divides the tasks’?

A Scrum team is dividing their work Azis is the Product Owner and has refined the product backlog He wants to assign the tasks to the Developers. The Developers want to choose their own tasks The Scrum Master agrees with the Product Owner

Is it a good idea it the Product Owner divides the tasks’?
A . Yes, because the Product Owner both understands the ordering and knows the Developers skills
B. Yes, because the Scrum Master and the Product Owner agree on who assigns work to the Developers
C. No, because the Scrum Master is accountable tor dividing product backlog items over the Developers
D. No, because this conflicts with the principle of self-management and the Developers do not agree

Answer: D

Latest ASM Dumps Valid Version with 39 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments