A loud hiss is coming from the audio system. This is MOST LIKELY caused by
- A . fluorescent lighting.
- B . poor gain structure.
- C . phase cancellation issues.
- D . the microphones being off.
On a construction project awarded through a competitive process, the electrical contractor says that the AV company is responsible for the installation of conduit.
What project document(s) would determine responsibility?
- A . estimate
- B . submittals
- C . proposal cover letter
- D . bid (tender) documents
Reverberant sound reaches the listener’s ears
- A . after
- B . before
- C . synchronized with
D at the same level as the direct sound.
One MAIN benefit of multicast over unicast in a network AV solution is it
- A . supports multi-channel audio.
- B . supports higher video resolutions.
- C . reduces network bandwidth when using multiple encoders.
- D . reduces network bandwidth when using multiple decoders.
What is the document that shows project tasks, indicating their allocated time, dependencies, and relationships between activities?
- A . flow chart
- B . Gantt chart
- C . needs analysis
- D . Venn diagram
An event planner for a banquet surrounding a swimming pool has requested that the pool be lit in the client’s colors using underwater lighting.
What does the technician need to consider?
- A . the IP rating of the fixtures
- B . access to a grounded power supply
- C . whether the installing technicians are PADI certified
- D . the ability to physically secure the fixtures underwater
Which of the following project management activities coordinates project requirements and resources?
- A . project budget
- B . logic model timeline
- C . logic network diagram
- D . project kick-off meeting
Which type of contract involves ongoing support for an AV system, regardless of the age of the facility or who did the initial installation?
- A . system warranty
- B . service agreement
- C . manufacturer warranty
- D . preventive maintenance
A task cannot begin before another task is completed.
How is this described in a project task schedule?
- A . requirement
- B . dependency
- C . consequence
- D . determination
For a design-bid (tender)-build project, the final step for determining the owner’s costs for an AV system is
- A . selecting an Integrator.
- B . performing a needs analysis.
- C . having the owner approve the design.
- D . ensuring the equipment specification isreadyforbid.