Network Quality of Service (QoS) is defined as
- A . the ability to prioritize the traffic in the network system.
- B . the ability to set the quantity of stations connected via the network.
- C . the ability to remotely manage network switches, routers and hubs via the network connection.
- D . a feature allowing the network administrator to monitor who is connected to the network at any given time.
A saeen is 144 in (3658 mm) wide and the throw ratio is 2.3:1.
How far from the screen should the projector be placed?
- A . 288 In (7303 mm)
- B . 302 in (7681 mm)
- C . 331 in (8413 mm)
- D . 446 in (11339 mm)
Which method of control is supported by HDBaseT?
- A . PCIE
- B . DAU
- C . RS-232
- D . DMX512
During project delivery and after completion, it is important to ensure correct management of control system code so that
- A . programming costs will be within project budget.
- B . other contractors are unable to reuse or edit code.
- C . the most up-to-date version of code is available for upload when required.
- D . sub-contract programmers submit uncompiled code as per their contract of employment.
Assuming a 10′ (3 m) ceiling, what is the approximate volume of this room?
- A . 300 cubic ft (8.5 m3)
- B . 600 cubic ft (17 m3)
- C . 1500 cubic ft (42.5 m3) o
- D . 6000 cubic ft (162 m3)
The BEST way to ensure that a project is on budget is to
- A . calculate the number of calendars days remaining to completion.
- B . visit the job site and determine the percentage of work completed.
- C . ask the installation team to estimate remaining work to completion.
- D . review accrued labor and material costs against remaining work.
Maintaining AV operations includes which of the following?
- A . conforming to DISCAS
- B . measuring system SPL
- C . updating control system firmware
- D . comparing NAG and PAG calculations
How frequently should a personal fall arrest harness be inspected?
- A . weekly
- B . before each use
- C . at the beginning of each project
- D . at the beginning of each work day
When discussing a proposed audiovisual project with a new customer, it is important for the salesperson to FIRST
- A . conduct a survey of end users to determine the project goals.
- B . prepare a detailed layout of the equipment and cabling requirements.
- C . identify the key decision makers and stakeholders in the client’s organization.
- D . consult with the project manager to determine the availability of staff to complete the installation.
Project documentation states the system must logically Isolate control and media networks.
What piece of network equipment should be used?
- A . router
- B . access point
- C . managed switch
- D . unmanaged switch