In which scenario should you set redundancy for master modules to be highly available?
You are creating a Logical Interconnect Group for a three-frame HPE Synergy solution with HPE Virtual Connect SE100Gb F32 Modules for Synergy.
In which scenario should you set redundancy for master modules to be highly available?
A . When storm control or loop protection will be enabled for Virtual Connect modules
B . When each of the frames has two Virtual Connect modules installed
C . When each Virtual Connect module is installed in different frame
D . When each Virtual Connect module is installed in different fabric
Answer: C