In which SAP Activate methodology phase does the team identify and design functional quick wins in scope of the conversion project? Please choose the correct answer.
In which SAP Activate methodology phase does the team identify and design functional quick wins in scope of the conversion project? Please choose the correct answer.
A . Realize
B . Deploy
C . Explore
D . Prepare
Answer: C