In which SAP Activate methodology phase does the team complete the Integration Validation? Please choose the correct answer.

In which SAP Activate methodology phase does the team complete the Integration Validation? Please choose the correct answer.
A . Realize
B . Deploy
C . Explore
D . Prepare

Answer: A