In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?
A . Product Description
B . Team Plan
C . Work Package
D . Stage Plan
Answer: C
Explanation:
In PRINCE2®, a Work Package is the document where the Project Manager defines the time and cost tolerances for the work assigned to a Team Manager. The Work Package provides detailed information on the products to be delivered, the reporting requirements, and the tolerances within which the Team Manager operates.
Reference: PRINCE2® Foundation official documentation and study materials.
Latest PRINCE2 7 Foundation Dumps Valid Version with 463 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund