In which Phase of the TOGAF ADM are the Architecture Roadmap and the Implementation and Migration Plan integrated with other change activity in the enterprise?
A . PhaseA
B . PhaseD
C . PhaseE
D . PhaseF
E . PhaseG
Answer: D