In which Phase of the TOGAF ADM are the Architecture Roadmap and the Implementation and Migration Plan integrated with other change activity in the enterprise?
In which Phase of the TOGAF ADM are the Architecture Roadmap and the Implementation and Migration Plan integrated with other change activity in the enterprise?
A . PhaseA
B . PhaseD
C . PhaseE
D . PhaseF
E . PhaseG
Answer: D