In which Phase of the TOGAF ADM are the Architecture Roadmap and the Implementation and Migration Plan integrated with other change activity in the enterprise?

In which Phase of the TOGAF ADM are the Architecture Roadmap and the Implementation and Migration Plan integrated with other change activity in the enterprise?
A . PhaseA
B . PhaseD
C . PhaseE
D . PhaseF
E . PhaseG

Answer: D

Latest OG0-093 Dumps Valid Version with 356 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments