In which phase of the SAP Activate Methodology does the team complete the System Assessment? Please choose the correct answer.
In which phase of the SAP Activate Methodology does the team complete the System Assessment? Please choose the correct answer.
A . Deploy
B . Explore
C . Prepare
D . Realize
Answer: C