In which part of the ADM cycle do building block gaps become associated with work packages that will address the gaps?
A . Phases G and H
B . Phases F
C . Phases B C and D
D . Phase E
Answer: D
Explanation:
In Phase E of the ADM cycle, building block gaps become associated with work packages that will address the gaps. This phase involves creating an Implementation and Migration Plan that defines a set of work packages and Transition Architectures that will deliver the Target Architecture.
Reference: The TOGAF® Standard | The Open Group Website, Section 3.2.5 Phase E: Opportunities & Solutions.