In which order are components reloaded during the process?
A network engineer needs to upgrade the EPLDs of the fabric modules for a Cisco MDS director-class switch.
In which order are components reloaded during the process?
A . one fabric module at the time
B . all fabric modules followed by the entire switching platform
C . all fabric modules in parallel
D . one module and one supervisor at the time
Answer: A
Explanation:
Option A is the correct order of reloading components during the process of upgrading the EPLDs of the fabric modules for a Cisco MDS director-class switch. The EPLD upgrade is performed on one fabric module at a time, and the fabric module is reloaded after the upgrade. The other fabric modules and the switching platform are not reloaded during the process.
Reference: Cisco MDS 9000 Family NX-OS Upgrade and Downgrade Guide, Release 8.x – Upgrading the EPLDs [Cisco MDS 9000 NX-OS and SAN-OS Software], Upgrading the EPLDs, Upgrading the EPLDs on a Cisco MDS 9700 Series Switch
Cisco MDS 9000 Family NX-OS Upgrade and Downgrade Guide, Release 8.x – Upgrading the EPLDs [Cisco MDS 9000 NX-OS and SAN-OS Software], Upgrading the EPLDs, Guidelines and Limitations for Upgrading the EPLDs
Latest 350-601 Dumps Valid Version with 138 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund