Exam4Training

In which of the following years does the project break even?

The table below shows the costs and savings associated with a project.

In which of the following years does the project break even?
A . Year 2.
B. Year 3.
C. Year 4.
D. The project does not pay back within the four year period

Answer: C

Exit mobile version