In which of the following SDLC phases would the IS auditor expect to find that controls have been incorporated into system specifications?
In which of the following SDLC phases would the IS auditor expect to find that controls have been incorporated into system specifications?
A . Development
B . Implementation
C . Design
D . Feasibility
Answer: B
Latest CISA Dumps Valid Version with 2694 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments