In which of the following phases would this Scrum process be in?

Andy, a Scrum Master, is helping his team draft a Sprint Backlog.

In which of the following phases would this Scrum process be in?
A . Initiate
B. Plan and Estimate
C. Implement
D. Review and Retrospect

Answer: B

Latest ASM Dumps Valid Version with 39 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments