In which of the following objects can you activate back flushing for production orders? (Choose three)
In which of the following objects can you activate back flushing for production orders? (Choose three)
A . Work center
B . Routing
C . Material master (finished product)
D . Material master (component)
E . Production scheduling profile
Answer: A,B,D