In which of the following levels do this identified risk exists?

You are the project manager in your enterprise. You have identified risk that is noticeable failure threatening the success of certain goals of your enterprise.

In which of the following levels do this identified risk exists?
A . Moderate risk
B . High risk
C . Extremely high risk
D . Low risk

Answer: A

Explanation:

Moderate risks are noticeable failure threatening the success of certain goals.

Incorrect Answers:

B: High risk is the significant failure impacting in certain goals not being met.

C: Extremely high risk are the risks that has large impact on enterprise and are most likely results in failure with severe consequences.

D: Low risks are the risk that results in certain unsuccessful goals.

Latest CRISC Dumps Valid Version with 933 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments