In which of the following documents can this information be found?
A project manager needs to identify the resources assigned to a particular task.
In which of the following documents can this information be found?
A . Project schedule
B . Cost plan
C . Scope statement
D . Impact assessment
Answer: A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 156
Latest PK0-004 Dumps Valid Version with 574 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments