In which of the following cases, would an organization be more prone to risk acceptance vs. risk mitigation?
A . The organization uses exclusively a quantitative process to measure risk
B . The organization uses exclusively a qualitative process to measure risk
C . The organization’s risk tolerance is high
D . The organization’s risk tolerance is lo
Answer: C