In what scenario will there be multiple resource requests for the same project role?
A . Multiple skills have been assigned to the same project role.
B . The resource assigned to the work package consists of multiple individual employees.
C . Multiple work items have been created for the same project role.
D . The estimated effort for the project role exceeds the work package duration.
Answer: C