In what process is the authorization to deliver the project’s products given?

In what process is the authorization to deliver the project’s products given?
A . Starting up a Project
B . Initiating a Project
C . Managing a Stage Boundary
D . Directing a Project

Answer: D

Explanation:

The authorization to deliver the project’s products is given during the Directing a Project process. This process involves the Project Board’s decision-making responsibilities, including granting permission to proceed with the project after the initiation phase and authorizing the delivery of stages as the project progresses.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources